Item | Project | Client | Owner | Description | Year |
1 | Pig Launcher | SADRA Co. | POGC PH22/24 | Engineering | 2012 |
2 | Pig Launcher | SADRA Co. | POGC-PH17&18 | Engineering | 2012 |
3 | Pig Launcher\Receiver | SAZEH Co. | POGC-PH12 | Engineering | 2012 |
4 | Fine Filter – Reshadat 530 m3/hr | SADRA Co. | I.O.O.C. | E.P.C. | 2012-2013 |
5 | Vacuum Deaerator Sirri 1050 m3/hr | Power Control Co. | I.O.O.C. | E.P.C. | 2012-2013 |
6 | Catalyst Recovery Bandar Abbas Gas Condensate Refinery | Faradast Energy Falat Co. | Persian Gulf Star Oil Co. | E.P.C. | 2013-2014 |
7 | Vacuum Deaerator Yadavaran 88 m3/hr | Jahan Pars Co. | SINOPEC | E.P.C. | 2013 |
8 | No.19-Sample Cooler Yadavaran | SINOPEC – S.S.K. | PEDEC | E.P.C | 2014 |
9 | No.93-Sample Connection Yadavarann | SINOPEC | PEDEC | E.P.C. | 2015 |
10 | Commissioning Of Steam Plant | Karoon Petrochemical Co. | N.I.P.C | Commissioning & Design of Control System (Logic) | 2015 |
11 | Commissioning Of Economizer | Arman Energy Co. | Tehran Refinery | Finalized Design Document & Management Of Erection & Commissioning | 2015 |
12 | Bid Boland Steam Deearator | Sazeh – Jahan Pars | SAED | Design- Procurement- Manufacturing- Commissioning | 2015 |
13 | Azar Vacuum Deaerator Package 38 m3/hr | Jahanpars Co. | PEDEC | Design- Procurement- Manufacturing- Commissioning | 2017 |
14 | No.2 Injection Package | Bou Ali Sina Petro Chemical Co. | Persian Gulf Holding | Design- Procurement- Manufacturing- Commissioning | 2017 |
15 | De-Gasing Water Treatment Niasar | Delta Kameron Co. | Kashan Water Organization | Design- Procurement- Manufacturing- Commissioning | 2017 |
16 | Design Of Esfahan Economizer | Tasha Co. | Esfahan Refinery | Design & Commissioning | 2019 |
17 | No. 22 Injection Nozzle | FARAB Co. | P.O.G.C | E.P.C | 2019 |
18 | No.2 Injection Package | Faradast Energy Falat Co | EIED / Persian Gulf Holding | E.P.C | 2019 |
19 | Refrigeration Package | Chagalesh Co. | Esfahan Refinery | E.P.C | 2020 |